11/4/200511/06/2004
Gemba Solutions: Tel: +44 (0)1455 222060, Web:
www.oeeimpact.co.uk
PRODUCTIVITY IMPROVEMENTS COME AS STANDARD

What is OEE
OEE = Availability (B/A) X Performance (D/C) X Quality (F/E)
Planned
Shift = 480min
A Planned Machine Production Time = 420min
B Actual Running Time = 373min
C
Theoretical Machine Production Rate = 22,380
D Actual Production Rate = 19,271
E Pieces Produced = 19,271
F Good Parts = 18,848
Planned Idle
Stoppages
Speed Loss
Wastage
OEE IMPACT
Product Programmable
(88.8%)
(86.1%)
(97.8%)
OEE
= Availability x Performance x Quality
= 88.8 x
86.1 x 97.8 = 74.8%